Try Before You Buy

Download a free sample of any of our exam questions and answers

  • 24/7 customer support, Secure shopping site
  • Free One year updates to match real exam scenarios
  • If you failed your exam after buying our products we will refund the full amount back to you.

Tested & Approved PMP Study Materials Download Free Updated 1975 Questions [Q647-Q670]

Share

Tested & Approved PMP Study Materials Download Free Updated 1975 Questions

Regular Free Updates PMP Dumps Real Exam Questions Test Engine


The PMP 2022 version exam has a revised content outline, which includes three domains: People, Process, and Business Environment. Each domain covers a set of knowledge areas that project managers need to be proficient in. PMP exam is based on the latest edition of the PMBOK Guide (Seventh Edition), which provides the foundation for the PMP certification.

 

NEW QUESTION # 647
A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?

  • A. Deliver business value as soon as possible
  • B. Emphasize the use of Kanban methodology.
  • C. Ensure the project sponsor is aware of the go-to market date
  • D. Implement a plan-do-check-act (PDCA) cycle

Answer: A

Explanation:
The project manager should take the action of delivering business value as soon as possible as a priority. This is because the project is aimed at increasing the commercial value of the product in a highly competitive market, which means that the project needs to deliver a viable solution that meets the customer needs and expectations quickly and effectively. By delivering business value as soon as possible, the project manager can also obtain early feedback, validate the assumptions and requirements, and make adjustments as needed.
This will help to improve the quality, performance, and satisfaction of the product, and to reduce the risk of waste, rework, and delays. The other options are not as important or relevant as delivering business value as soon as possible. Emphasizing the use of Kanban methodology may be helpful, but it is not a priority action, as it is a tool or technique, not a goal or outcome. Kanban is a visual system that helps to manage the flow of work and limit the work in progress, but it does not guarantee the delivery of business value. Ensuring the project sponsor is aware of the go-to market date is a good practice, but it is not a priority action, as it is a communication or reporting activity, not a delivery or execution activity. The go-to market date may also change depending on the feedback and changes in the market. Implementing a plan-do-check-act (PDCA) cycle is a useful approach, but it is not a priority action, as it is a process or framework, not a result or benefit.
The PDCA cycle is a method for continuous improvement that involves planning, doing, checking, and acting on the results, but it does not specify what business value to deliver or how to deliver it. References: PMBOK Guide, 6th edition, Chapter 1.2.6, 4.1.3, 5.1.3, Agile Practice Guide, 1st edition, Chapter 2.2.1, 2.3.1


NEW QUESTION # 648
An agile project has just started, and the backlog is being prioritized. The customer wants to prioritize business value over identified risks.
How should the customer's request be managed?

  • A. Create a risk value profile to track the relative importance of risks.
  • B. Log and track risks separately as only business value is important.
  • C. Accept risks as they decrease over a period of time.
  • D. Assess risks together with business value during prioritization.

Answer: D


NEW QUESTION # 649
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

  • A. Suggest to the product owner to execute the changes in a separate project
  • B. Accommodate the critical and urgent changes in the current iteration
  • C. Leverage the product owner to monitor the external environment
  • D. Ask the product owner to stop accommodating further changes to the scope

Answer: B

Explanation:
Agile project management is designed to handle continuous changes. The agile approach allows for flexibility and adaptability, making it well-suited to projects where the environment is dynamic and changes are frequent2. In an agile project, changes are not seen as disruptions but as opportunities for improvement1.
Therefore, the project manager should accommodate critical and urgent changes in the current iteration. This approach allows the team to respond to changes in a timely manner and ensures that the product or service being developed remains relevant and valuable1.
: = Agile Change Management: Overview, Principles, Best Practices, 10 Steps to Introduce Change Management into Agile Projects


NEW QUESTION # 650
After receiving the hardware components from a vendor that will be used later in the project, the project manager sends an email to the finance department to pay the vendor based on the agreed-upon contract. The project manager later discovers that some of the components do not work properly.
What should the project manager have done to avoid this?

  • A. Used the claim administration technique
  • B. Completed a performance inspection of the deliverables
  • C. Utilized expert judgment on workmanship
  • D. Spent more time planning for this task

Answer: A

Explanation:
Section: Planning


NEW QUESTION # 651
You are in the process of reviewing all change requests and controlling changes to deliverables and organizational process asset. All of the following are inputs you need EXCEPT:

  • A. Project management plan
  • B. Recommended defect repair
  • C. Project charter
  • D. Requested changes
  • E. Work performance information

Answer: C


NEW QUESTION # 652
When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?

  • A. Coordinate with the benefit owner to track and collect the missing data and build the KPIs.
  • B. Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.
  • C. Work with the business analysts to track and collect the missing data and build the KPIs.
  • D. Ask the program manager to track and collect the missing data and work to build the KPIs.

Answer: A

Explanation:
Explanation
If some KPIs are not yet defined, it means that there is a lack of clarity on how to measure the project benefits and outcomes. The project manager should coordinate with the benefit owner to track and collect the missing data and build the KPIs. The benefit owner is the person or group who is accountable for the realization of benefits from a project or program . They are responsible for defining, monitoring and reporting on the benefits and KPIs of the project1.


NEW QUESTION # 653
During which process group is the quality policy determined?

  • A. Executing
  • B. Controlling
  • C. Planning
  • D. Initiating

Answer: C


NEW QUESTION # 654
A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability to perform a what-if analysis in the tool based on the customer demand and forecast.
What should the project manager do next?

  • A. Analyze and negotiate with the executive steering committee regarding this new request.
  • B. Include the new capability to the product backlog and continue activities based on the current plan.
  • C. Perform an impact analysis on the schedule and budget based on the additional scope.
  • D. Revise the project schedule and budget based on the additional scope, and review with the team.

Answer: C

Explanation:
Explanation
According to the Agile Practice Guide, agile project management is an iterative approach to delivering a project throughout its life cycle. Agile projects embrace change and value customer feedback, but they also need to manage the impact of change on the project scope, schedule, cost, quality, and risk. One of the tools and techniques for managing change in agile projects is impact analysis, which involves assessing the effect of a change request on the project objectives and deliverables. The project manager should perform an impact analysis on the schedule and budget based on the additional scope requested by the executive steering committee, and communicate the results to the relevant stakeholders. This will help the project manager to determine the feasibility and desirability of the change, and to negotiate the best course of action with the executive steering committee and the project team. References:
Agile Practice Guide, Chapter 5: Implementing Agile: Creating an Agile Environment, pp. 77-97.
PMBOK Guide, Sixth Edition, Chapter 4: Project Integration Management, pp. 111-158.
PMP Exam Prep Coursebook, Chapter 4: Project Integration Management, pp. 4-1 - 4-24.


NEW QUESTION # 655
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

  • A. Scope reviews
  • B. Control chart
  • C. Scope audits
  • D. Quality audits

Answer: D


NEW QUESTION # 656
During project planning, a project manager meets with several departments to organize brainstorming sessions.
Which process does this describes?

  • A. Create Requirements Documentation
  • B. Collect Requirements
  • C. Define Scope
  • D. Identify Stakeholders

Answer: B


NEW QUESTION # 657
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

  • A. Work together daily as a team
  • B. Send communications to the entire team
  • C. Only share suggestions at the end of the sprint
  • D. Follow the sprint planning
  • E. Strive toward continuous improvement

Answer: A,D


NEW QUESTION # 658
A project manager invites the new CIO to a meeting to review a project's key deliverables. milestones, and roles and responsibilities. what is the project manager's purpose for this?

  • A. Planning communications management
  • B. Identifying stakeholders
  • C. Developing the project charter
  • D. Minimizing stakeholder resistance

Answer: D


NEW QUESTION # 659
Which of the following is a tool and technique used in all processes within Project Integration Management?

  • A. Records management system
  • B. Expert judgment
  • C. Project management software
  • D. Issue log

Answer: B


NEW QUESTION # 660
Which influence reflects an informal organization?

  • A. penalty
  • B. reward power
  • C. expert power
  • D. referent power
  • E. formal authority

Answer: D


NEW QUESTION # 661
At the end of a project, the project manager was asked to provide a performance rating of the project team members.
What should the project manager mainly make reference to?

  • A. Agreed-upon key performance indicators (KPIs)
  • B. Feedback from the project sponsor
  • C. Input from project stakeholders
  • D. Competencies of team members

Answer: A


NEW QUESTION # 662
A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested in the product design.
How should the project manager deal with this situation?

  • A. Engage the project stakeholder and ensure all requirements are captured.
  • B. Review the stakeholder engagement plan and communication strategy.
  • C. Escalate the issue to the project sponsor and seek assistance.
  • D. Review the product requirements and update the stakeholder register.

Answer: B

Explanation:
The stakeholder engagement plan and communication strategy are two key documents that guide the project manager in managing stakeholder expectations and interactions. The project manager should review these documents to identify the level of interest and influence of the stakeholder from the legal department, and determine the best way to communicate and involve them in the project. Escalating the issue to the project sponsor may not be necessary or appropriate at this stage, as the stakeholder may not be critical for the project success. Engaging the stakeholder and ensuring all requirements are captured may not be feasible or effective, as the stakeholder may not have any input or interest in the product design. Reviewing the product requirements and updating the stakeholder register may not address the root cause of the stakeholder's lack of participation, as these documents do not specify how to engage and communicate with the stakeholder. References:
* A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Seventh Edition, Chapter
13: Stakeholder Engagement, Section 13.2: Plan Stakeholder Engagement, Section 13.3: Manage Stakeholder Engagement, Section 13.4: Monitor Stakeholder Engagement
* Professional in Business Analysis (PMI-PBA) Handbook, Section 2.3: Domains and Tasks, Domain 2:
Planning, Task 5: Plan Stakeholder Engagement
* Professional in Business Analysis (PMI-PBA) Examination Content Outline, Domain 2: Planning, Task 5: Plan Stakeholder Engagement


NEW QUESTION # 663
You finished your project for a customer to implement a business software solution. All deliverables have been handed over and are already in use by the company. There is a minor last payment to be made by the customer on contract closure. You believe that it is now getting time to finally close the contract with the customer and then administratively close down the project.
You approached the customer this morning and found that they are reluctant to finally close the contract. But you do not exactly understand why. What should you not do?

  • A. Update all documents related to the project and the product so that they reflect the final specifications and the status of both the project and the product. Organize them in a fashion for easy access.
  • B. Make sure that there are no active purchase orders against the contract or any other pending obligations, requests or claims from either party which need to be resolved. Then insist on formal contract closure.
  • C. Focus on your next project and leave the customer the time to get familiar with the software. They will come back to you anyway after some weeks to terminate the contract and make the last payment.
  • D. Based on the contract and all documents which are relevant for the formal relationship with the customer, write a close-out report describing what was contractually required and what was obtained.

Answer: C


NEW QUESTION # 664
Management plans include all of the following except:

  • A. Scope baseline.
  • B. Job descriptions.
  • C. Organization of project.
  • D. Policies and procedures.
  • E. Linear responsibility charts.

Answer: A


NEW QUESTION # 665
At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning.
The product owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.
What should the project manager do?

  • A. Organize a workshop after the standup to assess the impact.
  • B. Ask the product owner to provide more details in the standup.
  • C. Prepare a budget change request for additional resources.
  • D. Create a new product backlog item for the next sprint planning.

Answer: A


NEW QUESTION # 666
A compliance manager announces a new policy issued by the government that may impact project development.
How should the project manager respond?

  • A. Analyze the circumstances that brought about this new policy.
  • B. Continue with project execution as per the previously approved project plan.
  • C. Address any blockers to the project due to this policy and resolve them.
  • D. Maximize delivery by including this policy in the process.

Answer: C

Explanation:
Comprehensive and Detailed Explanation:
When a new compliance policy is introduced, the project manager must evaluate how it may impact the project. Addressing blockers (obstacles that arise due to the new policy) ensures the project can continue progressing while maintaining compliance. This is a proactive approach to risk and issue management.
* A ignores a potential external constraint (noncompliance risk).
* B is vague and does not focus on risk response.
* D may be useful but is not immediately action-oriented.
* C aligns with risk management best practices.
References:
* PMBOK Guide - Seventh Edition, Risk Management Performance Domain
* PMI Governance and Compliance Best Practices
##############################################


NEW QUESTION # 667
Inputs to Identifying Stakeholders include:

  • A. Project charter, procurement documents, expert judgment, and organizational process assets.
  • B. Project charter, procurement documents, enterprise environmental factors, and organizational process assets.
  • C. Project charter, stakeholder analysis, enterprise environmental factors, and stakeholder management strategy.
  • D. Project charter, stakeholder analysis, enterprise environmental factors, and organizational process assets.

Answer: B

Explanation:
Section: Initiation
Explanation/Reference:


NEW QUESTION # 668
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations What should the project manager do?

  • A. Change the budgeting technique to a more accurate, bottom-up cost estimation.
  • B. Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate
  • C. Use soft skills to convince the project sponsor to approve the new budget estimate
  • D. Review the historical information and lessons learned from last year's project to justify the new budget estimate

Answer: C


NEW QUESTION # 669
A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the right opportunity to include daily standup meetings. The project team has never used such tools, and a few members are challenging the decision.
What should the project manager do in this situation?

  • A. Update the project schedule to consider a daily standup as part of the project design phase.
  • B. Request that new team members familiar with iterative approaches be assigned to this project.
  • C. Define the ground rules, responsibilities, and conflict management strategies.
  • D. Engage an external vendor to perform the design phase under an iterative approach.

Answer: C

Explanation:
According to the PMBOK Guide, daily standup meetings are a common tool used in agile and hybrid project management approaches. They are short, time-boxed meetings that allow the project team to communicate their progress, issues, and plans for the day. Daily standup meetings can enhance collaboration, transparency, and alignment among the project team members. However, some team members may resist or challenge the use of daily standup meetings, especially if they are not familiar with them or perceive them as a waste of time. In this situation, the project manager should define the ground rules, responsibilities, and conflict management strategies for the project team. The project manager should explain the purpose and benefits of daily standup meetings, and establish clear expectations and guidelines for their conduct. The project manager should also assign roles and responsibilities to the team members, such as facilitator, timekeeper, recorder, etc.
The project manager should also address any conflicts or issues that may arise from the use of daily standup meetings, and resolve them in a constructive and respectful manner. The project manager should not engage an external vendor, request new team members, or update the project schedule, as these actions may not address the root cause of the team's resistance or challenge to the daily standup meetings. References:
* PMBOK Guide, 6th edition, pages 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35,
36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, ...


NEW QUESTION # 670
......

Pass PMI PMP Exam in First Attempt Easily: https://www.validexam.com/PMP-latest-dumps.html

Practice Test Questions Verified Answers As Experienced in the Actual Test!: https://drive.google.com/open?id=1TYg8ltpvKaBzUJxLotGV7fo_LrI1etx0