SAP C_TSCM42_66 Exam Overview:
SAP C_TSCM42_66 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Shop Floor Control | - Goods movements and confirmations - Execution of production orders |
| Material Requirements Planning (MRP) | - MRP procedures and parameters - MRP evaluation and exception messages |
| Sales and Operations Planning (SOP) and Demand Management | - Demand management processes - Planning strategies |
| Capacity Planning | - Capacity evaluation - Capacity leveling |
| Production Planning Overview | - Master data in production planning - Organizational structures in PP |
| Production Orders | - Order confirmations and settlements - Order creation and processing |
C_TSCM42_66 Exam Questions Answered
Delivery is instant: payment triggers an automatic email within a minute — unlimited installations, and 24/7 customer assisting for any downloading or purchasing issue if nothing arrives within 2 hours. If you fail the corresponding C_TSCM42_66 exam within 60 days of purchase, choose your remedy: a full refund (scanned enrollment slip plus the official Score Report PDF within 2 days of the exam; processed within 7 days), waiting for the next updated version free, or a free change to two other equal-value dumps. Excluded: exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products.
Use the vendor's official registration channels:
The SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 is delivered Computer-based exam (online proctored or test center) — select whichever arrangement suits you when booking.
The SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 blueprint spans 6 domains — including Sales and Operations Planning (SOP) and Demand Management, Production Orders, Material Requirements Planning (MRP). Let the weightings direct your spare-time review; the full outline above lists every subtopic.
Yes — download the free SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 demo and evaluate the material before paying. Purchases include 365 days of free updates, each new version emailed immediately upon release; renew afterward at 50% off.
Basic knowledge of SAP ERP and production planning processes is recommended. Eligibility rules change periodically, so confirm the current requirements on the official page before registering.
Yes:
Courses give you the theory; the 80 practice questions for the SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 give you the rehearsal — every answer expert-verified.
The SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 is SAP's certification exam for SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6, at the Associate level. It validates job-ready skills, and passing it marks you as a verified professional.
SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 Sample Questions:
In which master data object do you set the standard values for an operation?
- A. Work Center
- B. Material Master
- C. Production Resource/Tool (PRT)
- D. Routing
Correct Answer: D 🗳️
You want to enhance the system statuses of a production order with user statuses.
How do you do this?
- A. Define the user statuses in the Customizing table of the system statuses.
- B. Define the user statuses in the order type-dependent parameters.
- C. Define a status profile in Customizing and assign it to the production scheduling profile.
- D. Define a status profile in Customizing and assign it to the order type.
Correct Answer: D 🗳️
You want to use the different options for planning in SAP ECC.
What is the correct sequence of the planning procedures?
- A. Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning
- B. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning
- C. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning
- D. Demand management -> Sales and operations planning -> Capacity planning -> Long-term planning -> Material requirements planning
Correct Answer: C 🗳️
For which of the following objects can you enter a confirmation?(Choose two)
- A. Production order
- B. Trigger Point
- C. Work Center
- D. Production order operation
Correct Answer: A,D 🗳️
Which of the following elements can be used in a process order?(Choose three)
- A. Parallel sequences
- B. Suboperations
- C. Phases
- D. Process instructions
- E. Relationships
Correct Answer: C,D,E 🗳️