Microsoft 074-343 Exam Overview:
| Certification Vendor: | Microsoft |
|---|---|
| Exam Name: | Managing Projects with Microsoft Project 2013 |
| Exam Number: | 74-343 |
| Exam Price: | Approximately USD 100 (varies by region) |
| Available Languages: | Spanish, Chinese (Simplified), English, Japanese, German, French |
| Passing Score: | 700/1000 |
| Exam Duration: | 50 minutes |
| Real Exam Qty: | 20-35 tasks (performance-based) |
| Certificate Validity Period: | Does not expire |
| Exam Format: | Task-driven assessment, Lab simulation, Performance-based |
| Related Certifications: | Microsoft Office Specialist (MOS) Project 2013 Expert |
| Recommended Training: | Microsoft Learn - Project training |
| Exam Registration: | Microsoft Certification Portal |
| Sample Questions: | ![]() |
| Exam Way: | Available via authorized test centers or online proctored delivery (where supported) |
| Pre Condition: | No formal prerequisites required, recommended familiarity with Microsoft Project 2013 |
| Official Syllabus URL: | https://learn.microsoft.com/en-us/credentials/ |
Microsoft 074-343 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Tracking Project Progress | - Monitoring and updating progress
|
| Topic 2: Managing Tasks | - Task creation and structure
|
| Topic 3: Managing Resources | - Resource allocation and optimization
|
| Topic 4: Reporting and Communication | - Project reporting tools
|
| Topic 5: Creating and Managing a Project | - Project file creation and configuration
|
About the Microsoft 074-343 Exam: FAQ
Delivery is instant: payment triggers an automatic email within a minute — unlimited installations, and 24/7 customer assisting for any downloading or purchasing issue if nothing arrives within 2 hours. If you fail the corresponding 074-343 exam within 60 days of purchase, choose your remedy: a full refund (scanned enrollment slip plus the official Score Report PDF within 2 days of the exam; processed within 7 days), waiting for the next updated version free, or a free change to two other equal-value dumps. Excluded: exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products.
50 minutes for 20-35 tasks (performance-based) questions. Fit the atmosphere in advance: timed sessions in the ValidExam online engine make the formal pace feel practiced, not pressured.
Use the vendor's official registration channels:
The Microsoft Managing Projects with Microsoft Project 2013 is delivered Available via authorized test centers or online proctored delivery (where supported) — select whichever arrangement suits you when booking.
The Microsoft Managing Projects with Microsoft Project 2013 blueprint spans 5 domains — including Tracking Project Progress, Creating and Managing a Project, Managing Tasks. Let the weightings direct your spare-time review; the full outline above lists every subtopic.
Yes — download the free Microsoft Managing Projects with Microsoft Project 2013 demo and evaluate the material before paying. Purchases include 365 days of free updates, each new version emailed immediately upon release; renew afterward at 50% off.
No formal prerequisites required, recommended familiarity with Microsoft Project 2013 Eligibility rules change periodically, so confirm the current requirements on the official page (official 074-343 exam page) before registering.
Yes:
Courses give you the theory; the 110 practice questions for the Microsoft Managing Projects with Microsoft Project 2013 give you the rehearsal — every answer expert-verified.
The Microsoft Managing Projects with Microsoft Project 2013 is Microsoft's certification exam for Microsoft Office Specialist (MOS) - Project 2013, at the Associate level. It validates job-ready skills, and passing it marks you as a verified professional. Related credentials include Microsoft Office Specialist (MOS) Project 2013 Expert.
Approximately USD 100 (varies by region) per attempt, 700/1000 to pass. A retake costs the full fee again — effective preparation with the 110 practice questions for the 074-343 exam is the economical path.
Microsoft Managing Projects with Microsoft Project 2013 Sample Questions:
You are a project manager who uses Microsoft project.
Your manager wants you to plan an office move. You have a project schedule from a prior office move named OfficeMove.mpp.
You need to create a new project schedule based on the old project schedule by performing the fewest steps possible.
What should you do?
- A. Open the old OfficeMove.mpp file and save the file using a new file name. Clear the baseline and set all tasks to zero percent complete.
- B. Open the old OfficeMove.mpp file and save the file using a new file name. Then, enter the project name in the Project Summary task. Set all tasks to zero percent complete.
- C. Open the Old OfficeMove.mpp file and change the project start date and project title.
Clear the baseline and save the file using the current project name. - D. Open the old OfficeMove.mpp file and save the file as Project template file. Create a new project using the template.
Correct Answer: A 🗳️
Explanation: Only visible for ValidExam members. You can sign-up / login (it's free).
You are a project manager for a large telecommunications company that uses Project Professional 2013.
The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task.
You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project.
What should you do?
- A. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 1. Change Fixed Cost Accrual to Start.
- B. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Prorated.
- C. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Start.
- D. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to End.
Correct Answer: B 🗳️
You are a project manager who uses Project Standard 2013.
You manage a large project and are capturing actual work for the tasks as they are being worked.
You do not need to enter the time on the actual day worked; however, you need to capture the total amount of time spent on the task.
The fixed work task has a baseline of 20 hours, and the developer's timecard displays the following hours:
* Monday = 2 hours
* Tuesday = 8 hours
* Wednesday = 4 hours
* Thursday = 2 hours
* Friday = 2 hours
The developer informs you that the task is now complete.
You need to update the actual work and mark the task complete.
What should you do?
- A. Open the Task Form and format it to show Schedule Details. Enter 18 hours in the Actual Work for the resource. Enter 2 hours in the remaining work. Mark the task as 100% complete.
- B. Open the Task Form and format it to show Schedule View. Enter 18 hours in the Work column for the resource.
- C. Open the Task Form and format it to show Work Details. Enter 20 hours in the Actual Work for the resource. Enter 0 hours in the remaining work. Mark the task as 100% complete.
- D. Open the Task Form and format it to show Work Details. Enter 18 hours in the Actual Work for the resource. Enter 0 hours in the remaining work.
Correct Answer: D 🗳️
You are a project manager who uses Project Professional 2013.
A senior stakeholder asks you to update your project to reflect your organization's scheduled two-week closure.
You need to reflect the closure within your schedule.
What should you do?
- A. Open the Project Calendar and modify the default work week by setting the dates as non-working time.
- B. Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.
- C. Create a new calendar and assign this to the tasks that are scheduled over the period of closure.
- D. Open the Project Calendar and enter the planned closure in the Exceptions tab.
Correct Answer: D 🗳️
You use Project Professional 2013 to manage a project for your organization.
You are tracking work in a project which contains a baseline and resource assignments.
You want to view the work variance for a specific resource for a specific task.
You need to choose a view that will show this information.
What should you do?
- A. View the Resource Sheet view and insert the Work Variance field.
- B. View the Resource Sheet that shows the Work table.
- C. View the Gantt chart in split view with Task form formatted to show Work Details.
- D. View the Task Usage view and insert the Work Variance column on the left side of the view.
Correct Answer: D 🗳️